Drawing to BOQpipeline control sheet
← Mindmapwhat the drawings said

Protective Platform

1 page · 4 crops · ancillary

Matched toInspection Platformbridge.ancillary_system.inspection_platformcheckon “Protective Platform”

4 not established
The class asks forValueHowFrom
LengthLwants m/mmnot establishedThe protective-platform notes require platforms at this site and reference Section 510 and a construction clearance diagram, but none of the supplied readings states or establishes a platform length.not found
WidthWwants m/mmnot establishedNo supplied reading gives a width or dimensions from which the protective-platform width can be derived.not found
Instance CountNwants countnot establishedThe note requires protective platforms at this site but gives no number of platforms; a count cannot be derived from the supplied readings.not found
Material TypeMATnot establishedNo material is specified for the protective platforms in the supplied readings. Section 510 is referenced, but its content is not included.not found

Worked out by openai/gpt-5.6-terra-pro from the readings below, which are the source. A derived value shows its arithmetic — check it against the drawing before it is priced.

How the sheets named it

protective platformsProtective platforms

Every dimension read for it5

  • 2021 EDITIONGeorgia Standard Specifications editionnot attributedp2 · p02_r11 left column list of specification and construction notes
  • 2024Supplemental specifications yearnot attributedp2 · p02_r11 left column list of specification and construction notes
  • 2021Georgia Standard Specifications editionnot attributedp2 · p02_r11
  • 2024Supplemental specifications yearnot attributedp2 · p02_r11
  • 510Georgia DOT Specifications sectionp2 · p02_r11

Notes on the sheets that carry it

  • p2SPECIFICATIONS - GEORGIA STANDARD SPECIFICATIONS, 2021 EDITION, AND 2024 SUPPLEMENTAL SPECIFICATIONS AS MODIFIED BY CONTRACT DOCUMENTS.
  • p2REINFORCING STEEL - PLACE AND TIE ALL REINFORCING STEEL IN ACCORDANCE WITH THE GEORGIA DOT SPECIFICATIONS. DO NOT WELD REINFORCING STEEL. MAINTAIN 2 INCH MINIMUM CLEARANCE ON ALL REINFORCEMENT UNLESS OTHERWISE NOTED.
  • p2CHAMFER - CHAMFER ALL EXPOSED CONCRETE EDGES 3/4" UNLESS OTHERWISE NOTED.
  • p2RAILROAD SIDE DITCHES - PRIOR TO THE BEGINNING OF CONSTRUCTION, CLEAN THE RAILROAD SIDE DITCHES IN THE CONSTRUCTION AREA IN SUCH A MANNER AS TO PROVIDE POSITIVE DRAINAGE. MAINTAIN THE RAILROAD SIDE DITCHES FREE OF SILT AND DEBRIS UNTIL FINAL ACCEPTANCE. SEE ROADWAY PLANS FOR EROSION CONTROL AND PAYMENT.
  • p2PROTECTIVE PLATFORMS - PROVIDE PROTECTIVE PLATFORMS AT THIS SITE, SEE SECTION 510 OF THE GEORGIA DOT SPECIFICATIONS. MAINTAIN A MINIMUM VERTICAL CLEARANCE AS DEFINED IN THE CONSTRUCTION CLEARANCE DIAGRAM.
  • p2TEMPORARY SHORING - INCLUDE THE COST OF TEMPORARY SHORING AS NECESSARY FOR BRIDGE CONSTRUCTION IN THE OVERALL BID SUBMITTED.
  • p2WAITING PERIOD - NONE REQUIRED.
  • p2FOUNDATION BACKFILL MATERIAL - PLACE 1'-0" OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2'-0" . USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.
  • p2PLAN DRIVING OBJECTIVE - SEE SUBSTRUCTURE DETAILS.
  • p2DRIVING RESISTANCE - DETERMINE DRIVING RESISTANCE FOR PILES USING DYNAMIC PILE TESTING IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATIONS. DYNAMIC PILE TESTING SHALL BE REQUIRED AT BRIDGE LEFT BENT 1 RIGHT, BRIDGE LEFT BENT 3 LEFT, BRIDGE RIGHT BENT 2 RIGHT AND BRIDGE RIGHT BENT 4 RIGHT.
  • p2DYNAMIC PILE TESTING - PERFORM PILE TESTING USING THE PILE DRIVING ANALYZER (PDA) IN ACCORDANCE WITH SPECIAL PROVISION SECTION 523. NOTIFY THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV TWO WEEKS PRIOR TO DRIVING PILES. SUBMIT ALL FILES REQUIRED BY SPECIAL PROVISION TO THE EMAIL ABOVE FOR REVIEW AND APPROVAL.
  • p2WAVE EQUATION - PERFORM WAVE EQUATION ANALYSIS (WEAP) IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATION. PROVIDE RESULTS OF THE WEAP TO THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV FOR REVIEW AND APPROVAL TWO WEEKS PRIOR TO DRIVING PILES.
  • p2FOUNDATION BACKFILL MATERIAL - PLACE 1’-0” OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND 3. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2’-0”. USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.

Every crop it was read in — the drawing beside what the model took off it

Page 2

crop

p02_r11 left column list of specification and construction notes

page 2 · gdot_plan_ab5a9057847f41e3bb9d0ead3c6f2c22_p02_r11_left_column_list_of_specification_and_construction_notes
Original
p02_r11 left column list of specification and construction notes
{
  "view": "Notes",
  "objects": [
    {
      "name": "reinforcing steel",
      "tag": "",
      "shape": "",
      "material": "steel",
      "count": null,
      "note": "Place and tie; do not weld. Maintain minimum clearance as noted."
    },
    {
      "name": "exposed concrete edges",
      "tag": "",
      "shape": "",
      "material": "concrete",
      "count": null,
      "note": "Chamfer all exposed edges unless otherwise noted."
    },
    {
      "name": "railroad side ditches",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Clean before construction and maintain free of silt and debris until final acceptance."
    },
    {
      "name": "protective platforms",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Provide at this site."
    },
    {
      "name": "temporary shoring",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Include cost as necessary for bridge construction in the overall bid."
    },
    {
      "name": "foundation backfill material",
      "tag": "BENTS 2",
      "shape": "",
      "material": "Type II foundation backfill material",
      "count": null,
      "note": "Place under each footing at Bents 2; use may be eliminated by the Engineer if the footing area is dry."
    },
    {
      "name": "footings",
      "tag": "BENTS 2",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Foundation backfill material is specified under each footing."
    },
    {
      "name": "piles",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Driving resistance, dynamic pile testing, and wave equation analysis are specified."
    },
    {
      "name": "bridge bents",
      "tag": "BRIDGE LEFT BENT 1 RIGHT; BRIDGE LEFT BENT 3 LEFT; BRIDGE RIGHT BENT 2 RIGHT; BRIDGE RIGHT BENT 4 RIGHT",
      "shape": "",
      "material": "",
      "count": 4,
      "note": "Dynamic pile testing is required at the listed bent locations."
    }
  ],
  "measurements": [
    {
      "label": "Georgia Standard Specifications edition",
      "value": "2021",
      "unit": "EDITION",
      "appliesTo": ""
    },
    {
      "label": "Supplemental specifications year",
      "value": "2024",
      "unit": "",
      "appliesTo": ""
    },
    {
      "label": "Minimum reinforcement clearance",
      "value": "2",
      "unit": "INCH",
      "appliesTo": "reinforcing steel"
    },
    {
      "label": "Chamfer size",
      "value": "3/4\"",
      "unit": "",
      "appliesTo": "exposed concrete edges"
    },
    {
      "label": "Foundation backfill thickness",
      "value": "1'-0\"",
      "unit": "",
      "appliesTo": "foundation backfill material"
    },
    {
      "label": "Foundation footing plan-dimension addition",
      "value": "2'-0\"",
      "unit": "",
      "appliesTo": "foundation backfill material"
    },
    {
      "label": "Notification/submittal period before driving piles",
      "value": "TWO",
      "unit": "WEEKS",
      "appliesTo": "piles"
    }
  ],
  "notes": [
    "SPECIFICATIONS - GEORGIA STANDARD SPECIFICATIONS, 2021 EDITION, AND 2024 SUPPLEMENTAL SPECIFICATIONS AS MODIFIED BY CONTRACT DOCUMENTS.",
    "REINFORCING STEEL - PLACE AND TIE ALL REINFORCING STEEL IN ACCORDANCE WITH THE GEORGIA DOT SPECIFICATIONS. DO NOT WELD REINFORCING STEEL. MAINTAIN 2 INCH MINIMUM CLEARANCE ON ALL REINFORCEMENT UNLESS OTHERWISE NOTED.",
    "CHAMFER - CHAMFER ALL EXPOSED CONCRETE EDGES 3/4\" UNLESS OTHERWISE NOTED.",
    "RAILROAD SIDE DITCHES - PRIOR TO THE BEGINNING OF CONSTRUCTION, CLEAN THE RAILROAD SIDE DITCHES IN THE CONSTRUCTION AREA IN SUCH A MANNER AS TO PROVIDE POSITIVE DRAINAGE. MAINTAIN THE RAILROAD SIDE DITCHES FREE OF SILT AND DEBRIS UNTIL FINAL ACCEPTANCE. SEE ROADWAY PLANS FOR EROSION CONTROL AND PAYMENT.",
    "PROTECTIVE PLATFORMS - PROVIDE PROTECTIVE PLATFORMS AT THIS SITE, SEE SECTION 510 OF THE GEORGIA DOT SPECIFICATIONS. MAINTAIN A MINIMUM VERTICAL CLEARANCE AS DEFINED IN THE CONSTRUCTION CLEARANCE DIAGRAM.",
    "TEMPORARY SHORING - INCLUDE THE COST OF TEMPORARY SHORING AS NECESSARY FOR BRIDGE CONSTRUCTION IN THE OVERALL BID SUBMITTED.",
    "WAITING PERIOD - NONE REQUIRED.",
    "FOUNDATION BACKFILL MATERIAL - PLACE 1'-0\" OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2'-0\" . USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.",
    "PLAN DRIVING OBJECTIVE - SEE SUBSTRUCTURE DETAILS.",
    "DRIVING RESISTANCE - DETERMINE DRIVING RESISTANCE FOR PILES USING DYNAMIC PILE TESTING IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATIONS. DYNAMIC PILE TESTING SHALL BE REQUIRED AT BRIDGE LEFT BENT 1 RIGHT, BRIDGE LEFT BENT 3 LEFT, BRIDGE RIGHT BENT 2 RIGHT AND BRIDGE RIGHT BENT 4 RIGHT.",
    "DYNAMIC PILE TESTING - PERFORM PILE TESTING USING THE PILE DRIVING ANALYZER (PDA) IN ACCORDANCE WITH SPECIAL PROVISION SECTION 523. NOTIFY THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV TWO WEEKS PRIOR TO DRIVING PILES. SUBMIT ALL FILES REQUIRED BY SPECIAL PROVISION TO THE EMAIL ABOVE FOR REVIEW AND APPROVAL.",
    "WAVE EQUATION - PERFORM WAVE EQUATION ANALYSIS (WEAP) IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATION. PROVIDE RESULTS OF THE WEAP TO THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV FOR REVIEW AND APPROVAL TWO WEEKS PRIOR TO DRIVING PILES."
  ],
  "labels": [
    "GENERAL NOTES"
  ],
  "description": "This crop is a General Notes block for bridge construction. It documents specification requirements, reinforcement and concrete edge treatment, drainage and protective-platform requirements, footing backfill, shoring, and pile-driving/testing requirements."
}

p02_r11 left column list of specification and construction notesNotes

  • protective platformsProvide at this site.

2021 EDITION Georgia Standard Specifications edition2024 Supplemental specifications year2 INCH Minimum reinforcement clearance3/4" Chamfer size1'-0" Foundation backfill thickness2'-0" Foundation footing plan-dimension additionTWO WEEKS Notification/submittal period before driving piles

crop

p02_r20 general notes

page 2 · gdot_plan_ab5a9057847f41e3bb9d0ead3c6f2c22_p02_r20_general_notes
Original
p02_r20 general notes
{
  "view": "Notes",
  "objects": [
    {
      "name": "protective platforms",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "To be provided at this site."
    },
    {
      "name": "temporary shoring",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "As necessary for bridge construction."
    },
    {
      "name": "foundation backfill material",
      "tag": "",
      "shape": "",
      "material": "Type II foundation backfill material",
      "count": null,
      "note": "Placed under each footing at Bents 2; text following “AND.” is as printed."
    },
    {
      "name": "footing",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Referenced in foundation backfill note."
    },
    {
      "name": "bent",
      "tag": "2",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Referenced in foundation backfill note."
    }
  ],
  "measurements": [
    {
      "label": "Foundation backfill thickness",
      "value": "1'-0\"",
      "unit": "",
      "appliesTo": "foundation backfill material"
    },
    {
      "label": "Plan footing dimensions allowance",
      "value": "2'-0\"",
      "unit": "",
      "appliesTo": "foundation backfill material"
    }
  ],
  "notes": [
    "PROTECTIVE PLATFORMS - PROVIDE PROTECTIVE PLATFORMS AT THIS SITE, SEE SECTION 510 OF THE GEORGIA DOT SPECIFICATIONS. MAINTAIN A MINIMUM VERTICAL CLEARANCE AS DEFINED IN THE CONSTRUCTION CLEARANCE DIAGRAM.",
    "TEMPORARY SHORING - INCLUDE THE COST OF TEMPORARY SHORING AS NECESSARY FOR BRIDGE CONSTRUCTION IN THE OVERALL BID SUBMITTED.",
    "WAITING PERIOD - NONE REQUIRED.",
    "FOUNDATION BACKFILL MATERIAL - PLACE 1'-0\" OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2'-0\". USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.",
    "PLAN DRIVING OBJECTIVE - SEE SUBSTRUCTURE DETAILS."
  ],
  "labels": [],
  "description": "This crop is a block of bridge construction notes. It addresses protective platforms, temporary shoring, waiting period, foundation backfill beneath footings at Bent 2, and the plan driving objective."
}

p02_r20 general notesNotes

  • protective platformsTo be provided at this site.

1'-0" Foundation backfill thickness2'-0" Plan footing dimensions allowance

crop

p02_r11

page 2 · general_construction_notes_p02_r11
Original
p02_r11
{
  "view": "Notes",
  "objects": [
    {
      "name": "reinforcing steel",
      "tag": "",
      "shape": "",
      "material": "steel",
      "count": null,
      "note": "Place and tie; welding is prohibited."
    },
    {
      "name": "exposed concrete edges",
      "tag": "",
      "shape": "",
      "material": "concrete",
      "count": null,
      "note": "Chamfer required unless otherwise noted."
    },
    {
      "name": "railroad side ditches",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Clean before construction and maintain free of silt and debris until final acceptance."
    },
    {
      "name": "protective platforms",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Provide at this site."
    },
    {
      "name": "temporary shoring",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Include cost as necessary for bridge construction in the overall bid."
    },
    {
      "name": "foundation backfill material",
      "tag": "TYPE II",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Place under each footing at Bents 2 and 3."
    },
    {
      "name": "footings",
      "tag": "BENTS 2 AND 3",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Foundation backfill material is specified beneath each footing."
    },
    {
      "name": "piles",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Driving resistance, dynamic pile testing, and wave equation analysis are specified."
    }
  ],
  "measurements": [
    {
      "label": "Georgia Standard Specifications edition",
      "value": "2021",
      "unit": "",
      "appliesTo": ""
    },
    {
      "label": "Supplemental specifications year",
      "value": "2024",
      "unit": "",
      "appliesTo": ""
    },
    {
      "label": "minimum reinforcement clearance",
      "value": "2",
      "unit": "INCH",
      "appliesTo": "reinforcing steel"
    },
    {
      "label": "concrete edge chamfer",
      "value": "3/4”",
      "unit": "",
      "appliesTo": "exposed concrete edges"
    },
    {
      "label": "foundation backfill thickness",
      "value": "1’-0”",
      "unit": "",
      "appliesTo": "TYPE II foundation backfill material"
    },
    {
      "label": "foundation backfill plan footing dimension addition",
      "value": "2’-0”",
      "unit": "",
      "appliesTo": "TYPE II foundation backfill material"
    },
    {
      "label": "Georgia DOT Specifications section",
      "value": "510",
      "unit": "",
      "appliesTo": "protective platforms"
    },
    {
      "label": "Georgia DOT Specifications sub-section",
      "value": "520.3.05.D.2",
      "unit": "",
      "appliesTo": "piles"
    },
    {
      "label": "Special Provision section",
      "value": "523",
      "unit": "",
      "appliesTo": "dynamic pile testing"
    },
    {
      "label": "notice/submittal period",
      "value": "TWO WEEKS",
      "unit": "",
      "appliesTo": "dynamic pile testing"
    },
    {
      "label": "Georgia DOT Specifications sub-section",
      "value": "520.3.05.D.2",
      "unit": "",
      "appliesTo": "wave equation analysis"
    },
    {
      "label": "review and approval submittal period",
      "value": "TWO WEEKS",
      "unit": "",
      "appliesTo": "wave equation analysis"
    }
  ],
  "notes": [
    "SPECIFICATIONS - GEORGIA STANDARD SPECIFICATIONS, 2021 EDITION, AND 2024 SUPPLEMENTAL SPECIFICATIONS AS MODIFIED BY CONTRACT DOCUMENTS.",
    "REINFORCING STEEL - PLACE AND TIE ALL REINFORCING STEEL IN ACCORDANCE WITH THE GEORGIA DOT SPECIFICATIONS. DO NOT WELD REINFORCING STEEL. MAINTAIN 2 INCH MINIMUM CLEARANCE ON ALL REINFORCEMENT UNLESS OTHERWISE NOTED.",
    "CHAMFER - CHAMFER ALL EXPOSED CONCRETE EDGES 3/4” UNLESS OTHERWISE NOTED.",
    "RAILROAD SIDE DITCHES - PRIOR TO THE BEGINNING OF CONSTRUCTION, CLEAN THE RAILROAD SIDE DITCHES IN THE CONSTRUCTION AREA IN SUCH A MANNER AS TO PROVIDE POSITIVE DRAINAGE. MAINTAIN THE RAILROAD SIDE DITCHES FREE OF SILT AND DEBRIS UNTIL FINAL ACCEPTANCE. SEE ROADWAY PLANS FOR EROSION CONTROL AND PAYMENT.",
    "PROTECTIVE PLATFORMS - PROVIDE PROTECTIVE PLATFORMS AT THIS SITE, SEE SECTION 510 OF THE GEORGIA DOT SPECIFICATIONS. MAINTAIN A MINIMUM VERTICAL CLEARANCE AS DEFINED IN THE CONSTRUCTION CLEARANCE DIAGRAM.",
    "TEMPORARY SHORING - INCLUDE THE COST OF TEMPORARY SHORING AS NECESSARY FOR BRIDGE CONSTRUCTION IN THE OVERALL BID SUBMITTED.",
    "WAITING PERIOD - NONE REQUIRED.",
    "FOUNDATION BACKFILL MATERIAL - PLACE 1’-0” OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND 3. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2’-0”. USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.",
    "PLAN DRIVING OBJECTIVE - SEE SUBSTRUCTURE DETAILS.",
    "DRIVING RESISTANCE - DETERMINE DRIVING RESISTANCE FOR PILES USING DYNAMIC PILE TESTING IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATIONS. DYNAMIC PILE TESTING SHALL BE REQUIRED AT BRIDGE LEFT BENT 1 RIGHT, BRIDGE LEFT BENT 3 LEFT, BRIDGE RIGHT BENT 2 RIGHT AND BRIDGE RIGHT BENT 4 RIGHT.",
    "DYNAMIC PILE TESTING - PERFORM PILE TESTING USING THE PILE DRIVING ANALYZER (PDA) IN ACCORDANCE WITH SPECIAL PROVISION SECTION 523. NOTIFY THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV TWO WEEKS PRIOR TO DRIVING PILES. SUBMIT ALL FILES REQUIRED BY SPECIAL PROVISION TO THE EMAIL ABOVE FOR REVIEW AND APPROVAL.",
    "WAVE EQUATION - PERFORM WAVE EQUATION ANALYSIS (WEAP) IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATION. PROVIDE RESULTS OF THE WEAP TO THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV FOR REVIEW AND APPROVAL TWO WEEKS PRIOR TO DRIVING PILES."
  ],
  "labels": [
    "GENERAL NOTES"
  ],
  "description": "This crop is a General Notes block for bridge construction. It documents general specifications, reinforcement and concrete requirements, railroad drainage, protective platforms, shoring, footing backfill, and pile-driving/testing requirements."
}

p02_r11Notes

  • protective platformsProvide at this site.

2021 Georgia Standard Specifications edition2024 Supplemental specifications year2 INCH minimum reinforcement clearance3/4” concrete edge chamfer1’-0” foundation backfill thickness2’-0” foundation backfill plan footing dimension addition510 Georgia DOT Specifications section520.3.05.D.2 Georgia DOT Specifications sub-section+4 more

crop

p02_r20

page 2 · protective_platform_note_p02_r20
Original
p02_r20
{
  "view": "Notes",
  "objects": [
    {
      "name": "Protective platforms",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "To be provided at this site."
    },
    {
      "name": "Temporary shoring",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "As necessary for bridge construction."
    },
    {
      "name": "Foundation backfill material",
      "tag": "TYPE II",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Specified beneath each footing at Bents 2, and [partial]."
    },
    {
      "name": "Footings",
      "tag": "",
      "shape": "",
      "material": "",
      "count": null,
      "note": "Referenced in foundation backfill note."
    }
  ],
  "measurements": [
    {
      "label": "Foundation backfill depth",
      "value": "1'-0\"",
      "unit": "",
      "appliesTo": "TYPE II foundation backfill material"
    },
    {
      "label": "Additional plan footing dimension allowance",
      "value": "2'-0\"",
      "unit": "",
      "appliesTo": "Footings"
    }
  ],
  "notes": [
    "PROTECTIVE PLATFORMS - PROVIDE PROTECTIVE PLATFORMS AT THIS SITE, SEE SECTION 510 OF THE GEORGIA DOT SPECIFICATIONS. MAINTAIN A MINIMUM VERTICAL CLEARANCE AS DEFINED IN THE CONSTRUCTION CLEARANCE DIAGRAM.",
    "TEMPORARY SHORING - INCLUDE THE COST OF TEMPORARY SHORING AS NECESSARY FOR BRIDGE CONSTRUCTION IN THE OVERALL BID SUBMITTED.",
    "WAITING PERIOD - NONE REQUIRED.",
    "FOUNDATION BACKFILL MATERIAL - PLACE 1'-0\" OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2'-0\". USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.",
    "PLAN DRIVING OBJECTIVE - SEE SUBSTRUCTURE DETAILS."
  ],
  "labels": [
    "SECTION 510 OF THE GEORGIA DOT SPECIFICATIONS",
    "CONSTRUCTION CLEARANCE DIAGRAM",
    "SUBSTRUCTURE DETAILS"
  ],
  "description": "This crop is a block of bridge construction notes. It documents requirements for protective platforms, temporary shoring, waiting period, foundation backfill beneath footings, and the plan driving objective; the bent reference in the foundation backfill note is visibly incomplete or malformed in this crop."
}

p02_r20Notes

  • Protective platformsTo be provided at this site.

1'-0" Foundation backfill depth2'-0" Additional plan footing dimension allowance