Matched toStructural Backfillbridge.approach_earthwork_system.structural_backfillon “Foundation backfill material”
| The class asks for | Value | How | From |
|---|---|---|---|
| VolumeVwants m3 | 53.52 m335 CY (Left Bridge) + 35 CY (Right Bridge) = 70 CY. 70 CY × 0.76455485798 m3/CY = 53.51884 m3, rounded to 53.52 m3.The Summary of Quantities identifies pay item 207-0203, Foundation backfill material, with 35 CY for each of the Left Bridge and Right Bridge. The required metric volume is derived by summing both bridge quantities and converting cubic yards to cubic metres. | derived | p2 · p02_r08 |
| Material TypeMAT | Type II -The foundation backfill material note expressly states that the material is "TYPE II FOUNDATION BACKFILL MATERIAL." | read | p2 · p02_r11 |
Worked out by openai/gpt-5.6-terra-pro from the readings below, which are the source. A derived value shows its arithmetic — check it against the drawing before it is priced.
How the sheets named it
Every dimension read for it10
- 35 CYLeft bridge quantity, foundation backfill materialp2 · p02_r08 pay item quantity table for left right bridges
- 35 CYRight bridge quantity, foundation backfill materialp2 · p02_r08 pay item quantity table for left right bridges
- 2021 EDITIONGeorgia Standard Specifications editionnot attributedp2 · p02_r11 left column list of specification and construction notes
- 2024Supplemental specifications yearnot attributedp2 · p02_r11 left column list of specification and construction notes
- 1'-0"Foundation backfill thicknessp2 · p02_r11 left column list of specification and construction notes
- 2'-0"Foundation footing plan-dimension additionp2 · p02_r11 left column list of specification and construction notes
- 1'-0"Foundation backfill thicknessp2 · p02_r20 general notes
- 2'-0"Plan footing dimensions allowancep2 · p02_r20 general notes
- 2021Georgia Standard Specifications editionnot attributedp2 · p02_r11
- 2024Supplemental specifications yearnot attributedp2 · p02_r11
Notes on the sheets that carry it
- p2SPECIFICATIONS - GEORGIA STANDARD SPECIFICATIONS, 2021 EDITION, AND 2024 SUPPLEMENTAL SPECIFICATIONS AS MODIFIED BY CONTRACT DOCUMENTS.
- p2REINFORCING STEEL - PLACE AND TIE ALL REINFORCING STEEL IN ACCORDANCE WITH THE GEORGIA DOT SPECIFICATIONS. DO NOT WELD REINFORCING STEEL. MAINTAIN 2 INCH MINIMUM CLEARANCE ON ALL REINFORCEMENT UNLESS OTHERWISE NOTED.
- p2CHAMFER - CHAMFER ALL EXPOSED CONCRETE EDGES 3/4" UNLESS OTHERWISE NOTED.
- p2RAILROAD SIDE DITCHES - PRIOR TO THE BEGINNING OF CONSTRUCTION, CLEAN THE RAILROAD SIDE DITCHES IN THE CONSTRUCTION AREA IN SUCH A MANNER AS TO PROVIDE POSITIVE DRAINAGE. MAINTAIN THE RAILROAD SIDE DITCHES FREE OF SILT AND DEBRIS UNTIL FINAL ACCEPTANCE. SEE ROADWAY PLANS FOR EROSION CONTROL AND PAYMENT.
- p2PROTECTIVE PLATFORMS - PROVIDE PROTECTIVE PLATFORMS AT THIS SITE, SEE SECTION 510 OF THE GEORGIA DOT SPECIFICATIONS. MAINTAIN A MINIMUM VERTICAL CLEARANCE AS DEFINED IN THE CONSTRUCTION CLEARANCE DIAGRAM.
- p2TEMPORARY SHORING - INCLUDE THE COST OF TEMPORARY SHORING AS NECESSARY FOR BRIDGE CONSTRUCTION IN THE OVERALL BID SUBMITTED.
- p2WAITING PERIOD - NONE REQUIRED.
- p2FOUNDATION BACKFILL MATERIAL - PLACE 1'-0" OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2'-0" . USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.
- p2PLAN DRIVING OBJECTIVE - SEE SUBSTRUCTURE DETAILS.
- p2DRIVING RESISTANCE - DETERMINE DRIVING RESISTANCE FOR PILES USING DYNAMIC PILE TESTING IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATIONS. DYNAMIC PILE TESTING SHALL BE REQUIRED AT BRIDGE LEFT BENT 1 RIGHT, BRIDGE LEFT BENT 3 LEFT, BRIDGE RIGHT BENT 2 RIGHT AND BRIDGE RIGHT BENT 4 RIGHT.
- p2DYNAMIC PILE TESTING - PERFORM PILE TESTING USING THE PILE DRIVING ANALYZER (PDA) IN ACCORDANCE WITH SPECIAL PROVISION SECTION 523. NOTIFY THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV TWO WEEKS PRIOR TO DRIVING PILES. SUBMIT ALL FILES REQUIRED BY SPECIAL PROVISION TO THE EMAIL ABOVE FOR REVIEW AND APPROVAL.
- p2WAVE EQUATION - PERFORM WAVE EQUATION ANALYSIS (WEAP) IN ACCORDANCE WITH SUB-SECTION 520.3.05.D.2 OF THE GEORGIA DOT SPECIFICATION. PROVIDE RESULTS OF THE WEAP TO THE GEOTECHNICAL BUREAU OF THE GEORGIA DOT OFFICE OF MATERIALS AND TESTING AT GEOTECHNICAL_SUBMITTALS@DOT.GA.GOV FOR REVIEW AND APPROVAL TWO WEEKS PRIOR TO DRIVING PILES.
- p2FOUNDATION BACKFILL MATERIAL - PLACE 1’-0” OF TYPE II FOUNDATION BACKFILL MATERIAL UNDER EACH FOOTING AT BENTS 2, AND 3. THE QUANTITY IS BASED ON THE PLAN FOOTING DIMENSIONS PLUS 2’-0”. USE OF THIS MATERIAL MAY BE ELIMINATED BY THE ENGINEER IF THE FOOTING AREA IS DRY.
Every crop it was read in — the drawing beside what the model took off it
Page 2
p02_r08
The merge put this crop under the item, but its reading names it differently — open the crop to see what it said.
p02_r08 pay item quantity table for left right bridgesTable
- Foundation backfill material207-0203Listed for left and right bridge.
35 CY Left bridge quantity, foundation backfill material35 CY Right bridge quantity, foundation backfill material295 CY Left bridge quantity, bridge excavation295 CY Right bridge quantity, bridge excavation811 SY Left bridge quantity, grooved concrete811 SY Right bridge quantity, grooved concreteLUMP LS Left bridge quantity, superstructure concreteLUMP LS Right bridge quantity, superstructure concrete+24 more
p02_r11 left column list of specification and construction notesNotes
- foundation backfill materialBENTS 2Type II foundation backfill materialPlace under each footing at Bents 2; use may be eliminated by the Engineer if the footing area is dry.
- footingsBENTS 2Foundation backfill material is specified under each footing.
2021 EDITION Georgia Standard Specifications edition2024 Supplemental specifications year2 INCH Minimum reinforcement clearance3/4" Chamfer size1'-0" Foundation backfill thickness2'-0" Foundation footing plan-dimension additionTWO WEEKS Notification/submittal period before driving piles
p02_r20 general notesNotes
- foundation backfill materialType II foundation backfill materialPlaced under each footing at Bents 2; text following “AND.” is as printed.
1'-0" Foundation backfill thickness2'-0" Plan footing dimensions allowance
p02_r11Notes
- foundation backfill materialTYPE IIPlace under each footing at Bents 2 and 3.
2021 Georgia Standard Specifications edition2024 Supplemental specifications year2 INCH minimum reinforcement clearance3/4” concrete edge chamfer1’-0” foundation backfill thickness2’-0” foundation backfill plan footing dimension addition510 Georgia DOT Specifications section520.3.05.D.2 Georgia DOT Specifications sub-section+4 more
p02_r20Notes
- Foundation backfill materialTYPE IISpecified beneath each footing at Bents 2, and [partial].
1'-0" Foundation backfill depth2'-0" Additional plan footing dimension allowance